Civic Center Storm Drain Repair

Project Overview

The Civic Center Storm Drain Repair Project consists of storm drain improvements in the Civic Center area that will promote the flow and circulation of stormwater into Legacy Park.

Project Status

Construction on the Project will begin March 18, 2020 with completion expected by April 10, 2020. Work hours will be Monday through Saturday, 7:00 AM to 4:00 PM.

Road Closure

Civic Center Way will be closed between Vista Pacifica St and the entrance to Malibu Cyn Village (west of Webb Way). Detours will remain in place throughout the duration of the project, including Sundays.

Northbound Detour on Civic Center Way (access via Webb Way)

This is provided as the main access to Malibu Cyn Village only

  • Two-way traffic will be available from Civic Center Way up to the driveway entrance of Malibu Canyon Village only (open at all times).
  • An alternative one-way exit only onto PCH via the existing onramp will be available for traffic.
  • No traffic will be allowed beyond this point with no access to Vista Pacifica St, Winter Canyon Rd, and Malibu Canyon Rd.

Southbound Detour on Civic Center Way (access via Malibu Cyn Rd)

This is provided as the main access to: Webster Elementary School / Malibu Seventh Day Adventist Church / Our Lady of Malibu Catholic Church and School / Vista Pacifica St and De Ville Way properties.

  • Two-way traffic will be available from Malibu Cyn Rd to Vista Pacifica St only
  • No traffic will be allowed beyond this point with no access to the Malibu Cyn Village.
  • Time of day restrictions for left turns from Malibu Cyn Rd onto Civic Center Way will be temporarily lifted.
  • Road access available: De Ville Way / Vista Pacifica St / Winter Cyn Rd